Teamlink Logo

Tallawong Village-Tallawong

Tallawong, NSW 2762
Tallawong Village-Tallawong - 1-15 & 2-12 Conferta AVE, Tallawong, NSW 2762, Image 0
Tallawong Village-Tallawong - 1-15 & 2-12 Conferta AVE, Tallawong, NSW 2762, Image 0
Tallawong Village-Tallawong - 1-15 & 2-12 Conferta AVE, Tallawong, NSW 2762
Tallawong Village-Tallawong - 1-15 & 2-12 Conferta AVE, Tallawong, NSW 2762
Tallawong Village-Tallawong - 1-15 & 2-12 Conferta AVE, Tallawong, NSW 2762
Tallawong Village-Tallawong - 1-15 & 2-12 Conferta AVE, Tallawong, NSW 2762

Project Overview

Contact agent
1
2
3

Tallawong Village Tallawong

Welcome to Tallawong Village in Sydney’s North West, adjacent to Tallawong Train Station. This exciting new hub will soon be home to almost 1,000 apartments and 30 retailers. The precinct will be buzzing with potential, with plenty of footfall for any retailer, comprising 9,000sqm of retail, commercial and community spaces, including a supermarket, central plaza and park. Tallawong Village combines a singular grand vision, of a rich diversity of connections and spaces for residents, workers, commuters and the broader community, with meticulous attention to the design and location of every component in the precinct. The result will be a vibrant retail destination, alive with possibilities and abuzz with footfall. Each retail tenancy will be perfectly poised to benefit from an active engagement with the surrounding street edges, parkways and laneways. Supermarket, food & beverage, convenience, dining, medical, childcare, gym, hair, beauty, meat, baked goods, or offices, whatever your business, retail or otherwise, this is your opportunity to service the many demands of thousands of local residents and workers.

Project Information

Address:

1-15 & 2-12 Conferta AVE, Tallawong, NSW 2762

Developer:DEICORP
Display Centre:Shop 30/12 Conferta AVE, Tallawong, NSW 2762Builder:DEICORP
Completion Date:Buildings A/B/C/D/E July/mid Aug 2024, QRS Q4 2024, FJ mid/late March 2025,K early April 2025, GH late April 2025Architect:TURNER STUDIO
Bedroom:1, 2, 3

Floor Plans

A-A.713-Tallawong Village-Tallawong
A-A.713-Tallawong Village-Tallawong
3
2
1
C-C.437-Tallawong Village-Tallawong
C-C.437-Tallawong Village-Tallawong
1
1
1

Construction Updates

Tallawong Village - Stage 2 & 3 Construction Update October 2024
Stage 2 – All façade works on the rear three buildings are complete and interiors are moving along nicely, with these buildings to be complete in the next month. The remaining 5 buildings of Stage 2 will be completed progressively following this. There are approximately 150 people on site daily working towards the completion of this stage of the project, including bricklayers and interior finishers as well as roadworks and infrastructure tradespeople. Stage 3 – The team are progressing with earthworks towards the back of the site, and on the front end, they are starting to pour slabs of the two basements. In the next three months, the team expect to have three buildings within Stage 2 completed, settled, and occupied for our purchasers, as well as progressing with basement slabs and starting on the superstructure of the buildings in Stage 3.
2024-10-20
https://teamlink-prod-all.oss-ap-southeast-1.aliyuncs.com/agency/1/product/6949/docs/1_10.png
More updates

Location

About Tallawong

Want to find out more about your new neighbourhood? Get all the information from our suburb profiles!
Tallawong Suburb Profile

Inspections

No available open inspection time
Book private inspection

Home Loan Calculator

ESTIMATED UPFRONT COSTS

$0

SAVINGS LEFT FOR DEPOSIT

$0

School Near By

NameTypeDistance
NameTypeDistance
NameTypeDistance
NameTypeDistance
Norway
HO
HOME789 Marketing
marketing@home789.com.au
BESbswy